While we had a slow start to the build because of excessive rain which made water management critical in order to create areas that we could work in, May has been a very productive month on site and we are currently casting the various slabs that form part of the basement. This will provide our residents with a safe, secure, and convenient space to park. Take a look at the progress here.
We asked our construction team for some facts on the build.
- Bulk earthworks was carried out by Icon Earthworks.
- Lateral support walls was carried out by Franki Africa and were completed on 17th February 2017.
- The main contractor on site is Group 5.
- Site was handed over to Group 5 in January 2017 with commencement of works 1st February 2017.
- To date we have cast 4800 m³ of concrete (Bases; columns; retaining walls; surface beds; slabs; lift cores)
We’re working hard to build an unparalleled urban living ideal for working professionals, first-time buyers, corporate long-stay tenants and property investors. Demand for residential property in Melrose Arch is at a premium, and One on Whiteley affords investors an exciting opportunity to benefit from excellent rental yields and capital growth in this sought-after location.
If you’re interested in buying a property at One On Whiteley, or have some questions about apartments, view the units here or contact Tersia Taljaard.